During the Spring, the following traffic management and road closures will be taking place.

Please be aware that these closure dates may change:


Works Area 11:
  • Junction 15a (1st March - Q2 2023)
Works Area 12:
  • Northampton Rd A508 Courteenhall Rd Junction (15th February to Q4 2023)
Works Area 13:
  • Blisworth Road (Road Closure Q1 - Q2 2023)
  • A508 Southern Roundabout (23rd January - Q3 2023)
Works Area 14:
  • Stratford Rd A508 Junction to Rookery Lane & Aston Road (27th February - Q4 2023)
Works Area 15:
  • A508 Northampton Road / Pury Road junction (Q2 - Q4 2023)
Works Area 16:
  • Blisworth Rd / Knock Ln & Stoke Rd (20th February - Q3 2023 | Road Closure Q1 - Q2 2023)
Works Area 17:
  • A508 Northampton Road / Church Lane Junction, Grafton Regis (Q2 - Q4 2023)

There will be pedestrian footway closures and diversions in place whilst we undertake the Roade Bypass construction.

The most up to date current and proposed traffic information can be found on the internet at: www.roadworks.org and www.trafficengland.com

SAT NAV: NN7 2QA

SLPN is strategically located in one of the UK’s most sought-after locations for industrial and logistics in the UK.

The site is situated immediately adjacent to the M1 Junction 15, providing rapid access to the national motorway network, with the ability to reach 90% of the UK population within 4 hours’ drive time.

Download the Directional Map below.

Traffic management will be in place during the works and will be maintained day and night.

A road sweeper will be in operation full time to ensure that the road into the site is kept clean. We would like to reassure you that we will work closely with the highways authorities to ensure any disruption is minimised and we will keep you regularly updated of any potential impacts.

You can view the Traffic Management sequence diagrams below.

2023 Traffic Management Sequence