Infrastructure Map

Pury Road

Works 15

Duration - 8 Weeks

Commencement - Jan 2023

Rookery Lane / Ashton Road

Works 14

Duration - 22 Weeks

Commencement - Aug 2022

Roade Bypass

Works 13

Duration - 64 Weeks

Commencement - Aug 2022

Knock Lane / Stoke Road
Works 16
Duration - 6 Weeks
Commencement - March 2023

Knock Lane / Stoke Road
Works 16
Duration - 6 Weeks
Commencement - March 2023

A508 Improvement
Works 12
Duration - 15 Weeks
Commencement - Feb 2023

Screening Bund
Works 6
Duration - 137 Weeks
Commencement - April 2021

A508 Access Rbt & Dualling
Works 7
Duration - 24 Weeks
Commencement - Jan 2021

Development Access Road
Works 5
Duration - 80 Weeks
Commencement - June 2021

Rail Terminal
Works 2
Duration - 53 Weeks
Commencement - July 2021

Rail Spur
Works 3
Duration - TBC
Commencement - TBC

Rail Connection
Works 1
Duration - 55 Weeks
Commencement - March 2021

Development Plateau
Works 4
Duration - 135 Weeks
Commencement - Jan 2021

Junction 15a Improvement
Works 11
Duration - 26 Weeks
Commencement - Aug 2022

J15 Smart Motorway Slip Road
Works 8 (2) (b)
Duration - 52 Weeks
Commencement - May 2020

J15 Construction
Works 8
Duration - 79 Weeks
Commencement - Jan 2021

J15 Smart Motorway Slip Road
Works 8 (2) (b)
Duration - 52 Weeks
Commencement - May 2020

Local Access
Works 9
Duration - 79 Weeks
Commencement - Jan 2021

Foul Rising Main
Works 10
Duration - 16 Weeks
Commencement - Jan 2021