Pury Road
Works 15
Duration - 8 Weeks
Commencement - Jan 2023
Rookery Lane / Ashton Road
Works 14
Duration - 22 Weeks
Commencement - Aug 2022
Roade Bypass
Works 13
Duration - 64 Weeks
Commencement - Aug 2022
Knock Lane / Stoke Road
Works 16
Duration - 6 Weeks
Commencement - March 2023
Knock Lane / Stoke Road
Works 16
Duration - 6 Weeks
Commencement - March 2023
A508 Improvement
Works 12
Duration - 15 Weeks
Commencement - Feb 2023
Screening Bund
Works 6
Duration - 137 Weeks
Commencement - April 2021
A508 Access Rbt & Dualling
Works 7
Duration - 24 Weeks
Commencement - Jan 2021
Development Access Road
Works 5
Duration - 80 Weeks
Commencement - June 2021
Rail Terminal
Works 2
Duration - 53 Weeks
Commencement - July 2021
Rail Spur
Works 3
Duration - TBC
Commencement - TBC
Rail Connection
Works 1
Duration - 55 Weeks
Commencement - March 2021
Development Plateau
Works 4
Duration - 135 Weeks
Commencement - Jan 2021
Junction 15a Improvement
Works 11
Duration - 26 Weeks
Commencement - Aug 2022
J15 Smart Motorway Slip Road
Works 8 (2) (b)
Duration - 52 Weeks
Commencement - May 2020
J15 Construction
Works 8
Duration - 79 Weeks
Commencement - Jan 2021
J15 Smart Motorway Slip Road
Works 8 (2) (b)
Duration - 52 Weeks
Commencement - May 2020
Local Access
Works 9
Duration - 79 Weeks
Commencement - Jan 2021
Foul Rising Main
Works 10
Duration - 16 Weeks
Commencement - Jan 2021